Schedule and Deliverables ------------------------------------------------------------------------------- Item Date ------------------------------------------------------------------------------- Finish sub-circuit layouts and simulations 08/09/96 Complete Elefant IC global layout 08/23/96 Finish chip level simulations 09/24/96 Submit Elefant IC to MOSIS 09/25/96 Receive bare die from MOSIS 11/25/96 Start testing of prototype front end assembly (w/ Elefant IC) Feb. 97 Preproduction submission of Elefant IC Apr. 97 System test w/ pre-production electronics Aug. 97 Production submission of Elefant IC Sep. 97 Installation of Drift Chamber Electronics Mar. 98 Deliverables ------------ Nov. 97 2000 Packaged Elefant Digitizer ICs. Jan. 98 1000 Tested, packaged Elefant Digitizer ICs.